Hilton Hotel Kawarau Falls
 
            Queenstown’s high influx of tourists every year creates high demand for 4-5 star luxury accommodation. Over the past 3 years, BDT has been involved in the design, construction, and commissioning aspects of Kawarau Falls Station Reserve, BDT’s second largest VRF project in New Zealand.
The Challenge
Queenstown’s high influx of tourists every year creates high demand for 4-5 star luxury accommodation. Over the past 3 years, BDT has been involved in the design, construction, and commissioning aspects of Kawarau Falls Station Reserve, BDT’s second largest VRF project in New Zealand.
The Solution
The Reserve North building was BDT’s very first water sourced condenser order of just over 2.1MW. This building was originally specified with another brand’s water sourced condensers, but the Mitsubishi Electric alternative proved to offer better low temperature performance, resulting in BDT securing the order. We believe that Reserve North is the largest water sourced job in the Southern Hemisphere. All of the systems have been commissioned by BDT in-house engineers to ensure the project is successfully set up right from the start. The hotel is finished to a very high standard and is rated as a 5 star hotel.
The second building on this site, Kingston West, is home to 96 MSZ-GE35VA High Wall Heat Pumps and achieves a 4 star hotel rating. To date, Mitsubishi Electric is the only air conditioning brand installed in Kawarau Falls Station reserve, supplying just over 2.4MW worth of equipment.
Total Capacity
            Heating Capacity: 2142 kW
            Cooling Capacity: 1904 kW
        
Outdoor Units
34 x PQRY-P500YGM-A Water Sourced Condensing Units
Indoor Units
            56x PEFY-VMH-E Ducted Units
            173 x PDFY-VM-E Ducted Units
            34 x PEFY-VMH-E-F Ducted Units
            59 x PLFY-VCM-E Four Way Cassettes
            25 x PLFY-P40VCM-E
            25 x PKFY-VBM-E Hi Wall Units
        
Wall Controllers
            260 x PAR-20MAA-G
            7 x PAC-SE41TS-E
        
Central Controller
            8 x G-50A-J
            8 x PAC-SC50KUA-F
            
            1 x BACnet BMS Interface Computer
        
Contractor
             
        
Publications
 City Multi New Zealand Showcase  - Edition 2.pdf (10,526 KB), City Multi New Zealand Showcase  - Edition 2.pdf (10,526 KB),
 Created: Monday 8th of September 2014
 City Multi New Zealand Showcase - Edition 1.pdf (7,386 KB), City Multi New Zealand Showcase - Edition 1.pdf (7,386 KB),
 Created: Tuesday 11th of June 2013
 City Multi World Wide Case Studies.pdf (3,184 KB), City Multi World Wide Case Studies.pdf (3,184 KB),
 Created: Wednesday 23rd of April 2008